Piece Cost
Piece Cost = Material Cost + Labor Cost +
Direct Overhead Cost + Logistics Cost +
Setup Cost + Other Direct Costs
-
Material cost (result of aggregating material costs from the current node’s children)
-
Labor cost (result of aggregating labor costs from the current node’s children)
-
Direct overhead cost: see Overhead Costs per Part
-
Logistics cost (result of aggregating logistics costs from the current node’s children)
-
Setup cost: also known as “amortized batch setup”, this is the result of aggregating setup costs from the current node’s children.
-
Other direct costs (see Other Direct Costs)